Wednesday, April 16, 2008

COME ON IN...THE BUILDING IS FINE!




Well, we had a set back with the roof the erectors installed. Let’s just say it was ALL WRONG. The steel roof had sags, sweeps and scratches…not to mention just outright bad workmanship. Thank the Lord for giving us a “prayed up” and knowledgeable building team, that caught the problem and took immediate action with our engineering company. The entire roof was removed and reinstalled with careful supervision. There is no cost to the church, but we will be about 6 weeks behind. In the scope of things 6 weeks is nothing compared to a lifetime free of leaks and rust!
The siding and windows are being installed. You can actually come inside and feel the size and envision the classrooms, gym, bathrooms (yea ladies!) and auditorium. The site work engineer has grated and leveled the road leading to our Education wing. The carport will be a blessing to our Mom’s with small children as they can drop them off and stay dry. Things are moving. We pray they will continue with no major set-backs.